The Elaine Wolf Theatre Construction Update – Week of September 12, 2011

Last week the steel awning went up that will be the support for our new marquee.  We began concrete demo on the interior of the theatre to make way for the new balcony.

Planned work this week includes more concrete demo on the area around our old box office and lighting booth.  There will be periods of heavy jack hammering – so be mindful if you are coming during the day to our business offices.  There will also be more work on the steel framing and sheeting outside.

For more construction photos or to see pictures from our groundbreaking ceremony “like” us on Facebook! www.facebook.com/maccjcc

GENERAL PROJECT INFORMATION:

We are delighted to announce that we have received a significant gift from Elaine Wolf for a major renovation of our mainstage theatre space.  The renovation will include a new balcony, accessible aisle, new stage, new electronic marquee, new lobby, new lighting and sound equipment and much more.  This summer we are working to complete all exterior elements of the project while the weather is warm.  Interior work will begin in August, once our summer program is completed.  A reminder that we are open for business during the entire construction period!!

We apologize in advance for our mess and any disruption this will cause (noise, parking, dust, etc).  Sometime in early 2012, we will proudly unveil the new state-of-the-art Elaine Wolf Theatre.